Nearly 8 miles of roads will be resurfaced this year. The tentative schedule is:
Monday, August 23
Gillin Road
Mercer Hill Road
Jefron Drive
Tuesday, August 24
Gordon Road
Paddock Road
Start Detweiler Lane/Graystone Road
Wednesday, August 25
Finish Detweiler Lane/Graystone Road
Brookfield Lane
Hogan Lane
Wolf Lane
Foxfield Court
Thursday, August 26
Ridings Way
Friday, August 27
Ivy Road
Whitpain Drive
Meade Road
Monday, August 30
Pemberton Road
Caslon Circle
Governor’s Way
Start Bradford Circle
Tuesday, August 31
Finish Bradford Circle
Narcissa Road
Wednesday, September 1
Creek View Lane
Lafayette Way
As with any paving operation, this work is very weather dependent and some streets on this year's schedule may not be resurfaced until 2022 if Mother Nature does not cooperate.
Please use caution when driving in work zones and observe all flaggers and signs.